Analisa Optimasi Biaya Dan Waktu Metode TCTO (Time Cost Trade Off) (Study Kasus: Preservasi Jalan Ruas Sp. Gunung Kemala – Sanggi)

  • Yusuf Aziz Irawan universitas sains dan alquran wonosobo
  • Suharto universitas sains dan alquran wonosobo
  • Agus Juara
Keywords: Acceleration, Critical Path

Abstract

The success of a project can be measured from two things, namely the benefits obtained and the timeliness of completion. In the implementation of the Gunung Kemala-Sanggi road preservation project, there are indications of delays where in contract 01 there is a remaining unfinished work resulting in contract 02, so it needs to be accelerated. This is intended so that this project can be completed more quickly according to the planned target. The acceleration method used is Time Cost Trade Off, with the alternative of adding 1 hour of overtime. This research methodology has several stages including primary data collection such as road preservation data and location data, as well as secondary data such as literature review, budget plan data (rab), project time schedule data, monthly report data. From the alternative results of adding overtime hours to the Kemala-Sanggi Mountain Road preservation project, it was found that the acceleration duration was 89 days from the previous duration of 112 days, 23 days faster so that the implementation of the work can be in accordance with the initial scheduling plan obtained from the project S curve. The reduction in the final total cost of the project due to acceleration is Rp. 687,273,911 so that the total cost of the project becomes Rp. 21,567.130,687. from the previous total value of Rp 22,186,544,124. It is hoped that further research can develop research on time cost trade off analysis, for example by developing an analysis by calculating labor overtime wages, operating costs of equipment when used for overtime or adding the number of tools.

References

R. Saputro, “‘ ANALISA PERCEPATAN DENGAN METODE TIME COST TRADE OFF PADA PROYEK PEMBANGUNAN HOTEL IJEN PADJAJARAN MALANG ’ SKRIPSI Disusun Oleh : FAKULTAS TEKNIK SIPIL DAN PERENCANAAN,” p. 2015, 2015.

A. Hardianto, “Analisa pengendalian manajemen waktu dan biaya proyek pembangunan hotel dengan network cpm studi kasus : batiqa hotel palembang,” Tek. Sipil dan Perenc., vol. 1, no. 1, pp. 1–17, 2015, [Online]. Available: http://eprints.ums.ac.id/37359/30/02. NASKAH PUBLIKASI.pdf.

N. Kartika, S. M. Robial, and A. Pratama, “Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Kolom Di Proyek Pembangunan Gedung Pemda Kabupaten Sukabumi,” J. Momen Tek. Sipil, vol. 3, no. 2, p. 103, 2021, doi: 10.35194/momen.v3i2.1207.

A. Kustirini, M. Qomaruddin, D. S. Budiningrum, and I. E. Andammaliek, “The Influence Of Compressive Strength Of Mortar Geopolimer On Addition Of Carbit Waste Ash With Curing Oven System,” in Proceedings of the 1st International Conference on Civil Engineering, Electrical Engineering, Information Systems, Information Technology, and Agricultural Technology, 2020, pp. 1–4.

F. N. Wowor, B. F. Sompie, D. R. O. Walangitan, and G. Y. Malingkas, “Aplikasi Microsoft Project dalam Pengendalian Waktu Pelaksanaan Pekerjaan Proyek,” J. Tek. Sipil, vol. 1, no. 8, pp. 543–548, 2013.

R. W. Kisworo, F. S. Handayani, and S. Sunarmasto, “ANALISIS PERCEPATAN PROYEK MENGGUNAKAN METODE TIME COST TRADE OFF DENGAN PENAMBAHAN JAM KERJA LEMBUR DAN JUMLAH ALAT,” 2016.

S. Asnuddin, J. Tjakra, and M. Sibi, “Penerapan Manajemen Konstruksi Pada Tahap Controlling Proyek,” J. Sipil Statik Vol.6 No.11, vol. 6, no. 11, pp. 895–906, 2018.

H. Manik, V. H. Puspasari, W. Nuswantoro, and A. Purwantoro, “Kunci Utama Pelaksanaan K3 Pada Proyek Pembangunan Gedung Muhammadiyah Palangka Raya Kampus II Di Saat Pandemi,” J. Civ. Eng. Study, vol. 1, pp. 1–5, 2021.

K. Umam, N. Hidayati, Y. A. Saputro, and D. F. Zaroh, “Kajian Sistem Manajemen K3 dan Tingkat Kecelakaan Kerja pada Pekerjaan Struktur Baja di Pltu Tanjung Jati B Unit 5 & 6 Jepara,” J. Disprotek, vol. 11, no. 2, pp. 93–101, 2020, doi: 10.34001/jdpt.v11i2.1164.

Y. Fahrizal, Y. A. Saputro, and D. Rochmanto, “Analisis Kepadatan Tanah Pada Akses Jalan Conveyor Pltu Tjb Unit 3 , 4 Dengan Menggunakan Standar Aashto T 191,” J. Civ. Eng. Study, vol. 02, pp. 42–48, 2022.

M. Qomaruddin, A. Ariyanto, I. Istianah, and F. Zahro, “Pemanfaatan Limbah Plastik Menjadi Agregat Pada Mortar Geopolimer,” Din. Rekayasa, Univ. Jenderal Soedirman, vol. 16, no. 2, 2020.

W. Iin, U. Khotibul, and R. Decky, “… Pembangunan Spal Dan Ipal Untuk Sarana Peningkatan Kualitas Lingkunga Kampung Nelayan Tanjungsari Kabupaten Rembang,” J. Civ. Eng. Study, vol. 02, no. 1, pp. 25–34, 2022, [Online]. Available: http://eprints.unisnu.ac.id/id/eprint/517/.

widayat Widayat, H. Satriadi, L. P. Wibawa, G. F. Hanif, and M. Qomaruddin, “Oil and gas characteristics of coal with pyrolysis process Oil and Gas Characteristics of Coal with Pyrolysis Process,” 2022, vol. 020077, no. July.

M. Qomaruddin and S. Sudarno, “The study of laminate concrete between geopolymer and conventional,” 2019, doi: 10.1088/1742-6596/1363/1/012011.

I. Susanto and N. Suaryana, “Evaluasi Kinerja Campuran Beraspal Lapis Aus (AC-WC) dengan Bahan Tambah Limbah Plastik Kresek,” J. Apl. Tek. Sipil, vol. 17, no. 2, p. 27, 2019, doi: 10.12962/j2579-891x.v17i2.4980.

Published
2022-11-08